Porter County commissioners deny NIPSCO's revised heavy-haul route and give first approval to higher development fees
Commissioners voted Nov. 17 against sending oversize transformer loads over 7.43 miles of county roads, citing repair costs the county cannot afford, and backed a roughly 40% development fee increase on first reading.
The Hoosier Wire · November 20, 2026 · Valparaiso, IN
The Porter County Board of Commissioners has denied a revised road agreement that would have routed NIPSCO's oversize transformer deliveries over 7.43 miles of county roads in Washington, Center and Union townships.
The revised route became necessary after the Indiana Department of Transportation withdrew permission for part of an earlier route over U.S. 30. The new proposal would have used roads including County Road 200 West, State Road 2 and County Road 150 West, also known as Hayes Leonard Road, to reach U.S. 30 and Joliet Road.
Commissioners raised concerns about damage to county roads and about what happens if damage appears months after hauling ends. They noted the county lacks the resources to repair roads each time they break, and questioned why a railroad spur could not be used instead. NIPSCO said the railroad declined to invest in the spur, and told the board on Nov. 19 it is evaluating the decision and will work with local, county and state agencies on next steps.
In the same meeting, the board approved on first reading an ordinance raising fees for the Department of Development and Storm Water Management by roughly 40% in general. The fees, which pay the department's salaries and benefits, were last set in 2019.
Because state law now requires a 180-day wait before such an increase takes effect, the new fees would not apply until about June 2027 if finally approved. The commissioners next meet Dec. 8.