Fort Wayne's City Council has put off a decision on replacing the city's aging asphalt plant, voting 6-3 to table a proposed $6,880,058 contract for a new facility.

Public Works Director Shan Gunawardena said the existing plant, built in 1998, needs a growing number of repairs, and that when equipment fails during paving season, crews can be forced to stop work. The plant makes the asphalt the city uses for paving streets and for the cold and hot mixes used in pothole repairs, and Gunawardena said buying those materials from a private supplier costs about $14 more per ton and leaves the city waiting behind the supplier's own customers.

Councilman Nathan Hartman, who voted to table the contract, said he is not opposed to the project but wants a clearer picture of the city's cash position and reserves before committing nearly $6.9 million. He noted the replacement had originally been planned for the 2028 budget. Councilman Russ Jehl also backed waiting, calling it a good project without a fiscal plan.

Council members Rohli Booker, Michelle Chambers and Geoff Paddock voted against tabling, arguing residents depend on reliable street repairs. Mayor Sharon Tucker criticized the delay in a statement after the vote, saying the project would directly benefit residents and neighborhoods.

Gunawardena told council a new plant would take about 15 to 16 months to build, and the contractor would need a notice to proceed by early December to be ready for the April 2028 paving season. The proposal was tabled with no set return date, though Gunawardena said he hopes council will reconsider it in January.